# Planning a Tracked Scissor Lift Job on a Slope: Set-Up, Travel and Unloading

> Canonical page: https://equiphire.com.au/tracked-scissor-lift-slope-planning/. Last updated 2 November 2026.

In September 2026 the Elevating Work Platform Association released supplementary guidance on the safe use of crawler-track EWPs, covering their operating characteristics, stability, hazard controls and the risks of loading and unloading. It is written for owners, operators, trainers and supervisors, and it should be read alongside the EWPA Good Practice Guide.

This page is the hirer's side of that planning, for the four tracked scissor lifts we hire out. It does not repeat the guidance. It sets out how each machine levels, what that changes about the set-up, and what we need from you before the truck is booked. If you are still deciding whether you need tracks at all, start with Tracked Scissor Lift Hire: Ground, Slopes and Access.

## The two ways our tracked lifts level

- On outriggers: set up and stay. The Zoomlion ZS0612C and LGMG SC0610EL-2 track to the position, lower four outrigger feet to bring the chassis level, then lift. To move, the platform comes down and the feet come up first.
- On the tracks: level and keep driving. The Almac Athena 850BL and Athena 870 BL EVO level the undercarriage itself, with no outriggers, and can keep driving while levelled.

Neither method is better in general. The method changes how the job is planned, and that is what the rest of this page works through.

Which levelling method suits the jobThe job | Usually suits | Why |

One spot, or a few separate spots | Outrigger machine (ZS0612C, SC0610EL-2) | One set-up per spot, battery electric, narrower |

Work that runs along a slope | Athena 850BL or 870 BL EVO | Levels on the tracks and keeps driving, no re-set at each position |

Tight route under about 1 m wide | SC0610EL-2 | The narrowest of the four, at 0.996 m |

Work that needs reach over an obstacle | A boom lift, not a tracked scissor | A scissor lifts straight up; see boom lift hire |

## Plan it in six steps

### 1. Mark every work position

Walk the job and mark where the platform needs to be. One spot, or a few separate spots, suits an outrigger machine: one set-up per spot. Work that runs continuously along a slope, such as gutters on a building on a fall or a fence line down a hill, suits an Athena, because it saves a full set-up at every position.

### 2. Measure the fall at each position

Two figures get confused. Gradeability is what a machine can travel up or down while stowed. The working slope is the ground it can level on and lift from, and it is the one that decides whether the job is possible.

- ZS0612C: working slope 12 degrees side to side and 7 degrees front to back on its outriggers, 30 per cent travel gradeability.
- Athena 850BL and 870 BL EVO: undercarriage levels up to 16 degrees front, 20 degrees rear and 15 degrees side to side on the Almac sheet.
- SC0610EL-2: 30 per cent stowed gradeability on the sheet; for its working slope the manual governs.

A phone level app on a straight board across the standing position is enough for us to check. Send the reading with a photo. If the machine will not lift, the tilt alarm is doing its job: the position is wrong.

### 3. Check the set-up space, not just the machine width

The width in the table below is the machine stowed, for getting through a gate. An outrigger machine needs more room than that once its feet are down, and each foot needs firm ground to land on. Send a photo of the standing position with a tape across it, and tell us about walls, garden edges, pits or kerbs beside it. We check the deployed footprint against the manual for that unit before booking.

### 4. Check what is under every foot and track

Levelling only works if the ground holds. An outrigger foot puts the machine's weight onto a small patch, so a soft spot, pit lid, trench line or fresh fill under one foot matters more than the surface around it. Plan spreader plates where the manual calls for them and on any ground you are unsure of. Tracks spread the load better than wheels, but they do not make saturated ground, an unknown suspended slab or a steep slope safe. The ground conditions guide covers what to look for, and when to get the ground assessed.

### 5. Plan the travel between positions and where it comes off the truck

With an outrigger machine, every move is stow, raise the feet, track, level again, so plan the route between positions on ground the machine can travel stowed. With an Athena, plan the line along the slope and check it stays within the machine's limits for the whole run, not just at the start.

The EWPA guidance singles out loading and unloading as a critical risk for crawler machines. Tell us where the truck can stop: a firm, level spot, clear of traffic and overhead lines, with a route from there to the work that the machine can travel stowed. The weights below are the machine alone, from the specification sheets.

### 6. Confirm power and wind

The ZS0612C and SC0610EL-2 are battery electric. Both Athenas we hire out run on a lead from a 15 amp outlet or on their Kubota diesel engine, with no on-board battery, so on electric power they work only within reach of the lead. Every machine has a maximum wind speed on its plate; if the job is exposed, tell us and we will confirm the limit for that model.

## The four machines side by side

Tracked scissor lifts in the Equip Hire fleet, from the manufacturer sheetsMachine | Levels on | Drives levelled | Working height | Stowed width | Weight | Power |

Zoomlion ZS0612C | Outriggers | No | 7.8 m | 1.15 m | 1,820 kg | Battery |

LGMG SC0610EL-2 | Outriggers | No | 8.8 m | 0.996 m | 1,600 kg | Battery |

Almac Athena 850BL | Tracks | Yes | 7.9 m | 1.30 m | 2,520 kg | 15 A lead or diesel |

Almac Athena 870 BL EVO | Tracks | Yes | 7.9 m | 1.30 to 1.50 m | 2,460 kg | 15 A lead or diesel |

None of the four fits a standard 0.82 m personnel doorway. The Athena comparison covers the two Athena baskets, and tracked vs rough terrain covers open sites that need more height or capacity. Real jobs: an Athena on rough, uneven ground.

## What to send us

- The site address and where the truck can stop.
- Each work position, and whether the work stays at one spot or runs along the slope.
- The fall at each position, with a photo.
- A photo of each standing position with a tape across it.
- The ground: dirt, gravel, turf, pavers, fill, any pits or trenches.
- The narrowest point on the route from the truck to the work.
- Power available on site, and whether the work is exposed to wind.

Describe the site for a quote, or use help me choose and tick the slope box. We check the machine against the site before booking. The site checklist has a printable record sheet for the rest of the job.

## Can I share this page?

Yes. Link to it from your site pack, SWMS references or training notes. Please link to this page rather than copying the table, so people see the current figures if a machine changes.

Machine figures from the Zoomlion, LGMG and Almac specification sheets held on file for the units we hire. Slope and wind limits are the manufacturer's; the plate and operator manual on the machine govern. This page is general information, not a substitute for the EWPA guidance or your own site risk assessment.

## Hire for this job

- [Tracked and self-levelling scissor lift hire](https://equiphire.com.au/equipment-hire/tracked-scissor-lifts/)

Not sure which machine? Tell us about the job. Add dates and a suburb if known, and we will help choose the machine and quote delivery.

---
Markdown copy of https://equiphire.com.au/tracked-scissor-lift-slope-planning/ (the HTML page is canonical). Generated 2026-11-19T19:19:11+00:00. Index: https://equiphire.com.au/llms.txt